title: "When something goes wrong: protecting your PI position"
description: "Claims made cover, early notification, first responses, admissions, Letters of Claim, adjudication and court proceedings."
url: "https://hpic-production.up.railway.app/design-and-construct/construction-pi-claims/"
updated: "2026-11-16T21:17:31.891Z"
---

[Home](https://hpic-production.up.railway.app/index.md) / [Who we cover](https://hpic-production.up.railway.app/who-we-cover.md) / [Design and construct](https://hpic-production.up.railway.app/design-and-construct.md) / Claims and notification

Technical guidance | Claims

# When something goes wrong: protecting your PI position

A concern about professional work does not always begin with a formal claim. It can start as a complaint, a request to investigate, a defect report or an allegation that something has not performed as expected.

On this page

A complaint is not just a complaintThe first responseWhen a concern arrivesFormal noticesRun-off

Last reviewed 11 November 2026 by Numan, Director, Hammond PI.

## A complaint is not always just a complaint

A client may raise an issue without asking for money. That does not put it outside the policy's notification requirements. The nature of the allegation, the potential for a claim and the definitions in your actual wording decide whether you need to notify. Do not wait for responsibility to be established before seeking advice, and remember that telling a colleague is not notice to insurers.

Illustrative scenario

A client says a finished room fails its acoustic requirement and alleges a design error. The cause might be design, installation, a later change or several factors. The allegation alone can be a notifiable circumstance.

## The first response matters

Appropriate acknowledgement

"Thank you for raising this. We are investigating and will respond further."

Potentially problematic commitment

"This was our design error. We will pay for the replacement."

The first reply acknowledges the concern without admitting responsibility or committing to a remedy. PI policies commonly restrict admissions, offers and settlements made without insurer consent. Where there is an urgent safety issue, protective steps should still be taken, with prompt escalation and careful records.

## What to do when a concern arrives

1.  **Record**Keep the original allegation, drawings, calculations, revisions, photographs and correspondence.
2.  **Establish**Write a factual chronology: dates, parties, services and events.
3.  **Refer**Contact us promptly with the documents. An internal report is not notice to insurers.
4.  **Notify**Make sure the right insurer receives valid written notice under the policy, and any excess layer insurers where relevant.
5.  **Coordinate**Get agreement before admissions, settlements, remedial commitments or appointing representatives, subject to urgent protective needs.

## Formal notices need immediate attention

A Letter of Claim, an adjudication notice or referral, or court proceedings can start tight procedural deadlines. Forward them in full, with all attachments, as soon as they arrive. Do not wait for a procedural deadline before contacting us; have the protocol, court or adjudication deadline checked straight away. For qualifying construction disputes, the statutory process provides for appointment and referral within seven days of notice and normally a decision within 28 days of referral. The referring party may consent to a further 14 days. Both parties may agree a longer period after referral. Check the applicable procedure immediately. If you are thinking of starting an adjudication yourself, take advice first.

## Why run-off cover matters

A design prepared today could lead to a claim many years from now. If the firm has stopped trading or no longer holds relevant PI by then, that protection may be missing. Arrange run-off before the existing policy expires or the business stops the professional work.

For qualifying dwelling claims in England and Wales under section 1 of the Defective Premises Act, the period is generally thirty years for rights accruing before 28 June 2022 and fifteen years thereafter. Section 2A applies prospectively to qualifying work on existing dwellings, with fifteen years. These periods do not extend insurance. In England and Wales, simple contract claims normally have six years from breach and actions on a deed normally twelve. For negligence involving latent damage, three years from the relevant knowledge may apply, subject generally to a fifteen year longstop from the relevant act or omission. Obtain advice on accrual and exceptions. Do not assume a later policy will repair a gap or cover a matter already known. When arranging or renewing cover, disclose material circumstances you know or ought to know; this does not replace notification under your existing policy. See [fair presentation](https://hpic-production.up.railway.app/design-and-construct.md).

[Claims guide for policyholdersPDF, 2 pages](https://hpic-production.up.railway.app/docs/claims-guide.pdf)

Already a client? [Report a claim or circumstance](https://hpic-production.up.railway.app/claims-support.md), or call us on [0333 222 4257](tel:03332224257).

The earlier a concern is recognised and referred, the greater the chance to preserve evidence, meet notification requirements and manage the response properly.

Terms used: [claims made](https://hpic-production.up.railway.app/design-and-construct.md), [notification of circumstances](https://hpic-production.up.railway.app/design-and-construct.md), [run-off cover](https://hpic-production.up.railway.app/design-and-construct.md).

## Related guidance

[GuideWho is responsible for the design?](https://hpic-production.up.railway.app/design-and-construct/design-responsibility.md)[GuideWhen your contract promises more than your PI covers](https://hpic-production.up.railway.app/design-and-construct/contractual-liability.md)[GuideIs your consultant's PI actually adequate?](https://hpic-production.up.railway.app/design-and-construct/checking-consultant-pi.md)[HubAll construction guidance and the glossary](https://hpic-production.up.railway.app/design-and-construct.md)

## Speak to us about a potential PI claim

Tell us about your professional activities, your insurance or the obligation you have been asked to accept. We explain the insurance implications and the terms available; legal interpretation or drafting needs a solicitor.

[Speak to Hammond PI](https://hpic-production.up.railway.app/contact.md)[Send a contract for review](https://hpic-production.up.railway.app/contract-reviews.md)[Get a PI quote](https://hpic-production.up.railway.app/quote.md)

This guidance is provided for general information and does not constitute legal advice or confirmation of insurance cover. Cover is subject to the terms, conditions and exclusions of the relevant policy. Contractual obligations should be considered with appropriate professional advice.