[Home](https://www.hammondpi.com/index.md) / [Insights](https://www.hammondpi.com/insights.md) / Chasing fees: how an architect’s fee dispute becomes an adjudication

Insights for architects

# Chasing fees: how an architect’s fee dispute becomes an adjudication

A design claim does not always start with a letter about a defect. It can arrive as the answer to your own fee demand: a counterclaim for negligent design, served as a notice of adjudication, with a decision due in weeks.

Why feesThe timetableThree disputesPolicy conditionsBefore you chaseThe decision

Guidance only. Cover depends on your own policy wording; speak to us about your position.

## Why a fee demand can start the claim

A client who is unhappy with the drawings, the programme or the cost does not always complain. Often it simply stops paying. When the practice presses for its money, the complaints are put in writing for the first time, usually as a set off against the fees and a counterclaim for more.

From that moment there are two disputes, not one. The first is a debt, which PI does not usually pursue for you. The second is an allegation of professional negligence, which is what PI is for. They will be argued together, in one place, and often on the client’s timetable.

## How adjudication works, and how fast

An architect’s appointment is a construction contract under the Construction Act, because the Act includes agreements to do architectural, design or surveying work in relation to construction operations ([Housing Grants, Construction and Regeneration Act 1996, section 104](https://www.legislation.gov.uk/ukpga/1996/53/section/104)). Either party therefore has a statutory right to refer a dispute to adjudication ([section 108](https://www.legislation.gov.uk/ukpga/1996/53/section/108)). Where the appointment has no compliant procedure of its own, the statutory Scheme applies ([Scheme for Construction Contracts, Part I](https://www.legislation.gov.uk/uksi/1998/649/schedule/part/I)).

The stages of a statutory adjudication and what each means for an architect

Stage

What the law says

What it means for you

Notice

A party may give notice at any time of its intention to refer a dispute

It can arrive without warning, including the week after your final demand

Referral

The dispute is to be referred to the adjudicator within 7 days of the notice

The client’s full case, with its evidence, follows almost at once

Your response

The Scheme fixes no period. The adjudicator gives directions on the timetable and deadlines, and may carry on without a party that misses them

You may have days to answer a case prepared over months

Decision

Within 28 days of referral. The adjudicator may add up to 14 days, but only with the consent of the party that referred the dispute

The party that started the process controls whether there is more time

Effect

The decision is binding until the dispute is finally determined by legal proceedings, arbitration or agreement

A sum awarded usually has to be paid first and argued about afterwards

One exception matters to practices with private clients. The Act’s adjudication provisions do not apply to a contract with a residential occupier, meaning one that principally relates to work on a dwelling that a party occupies or intends to occupy as a home ([section 106](https://www.legislation.gov.uk/ukpga/1996/53/section/106)). A homeowner has no statutory right to adjudicate against you, but your appointment may give one by its own terms. Check the form you use.

## One notice, three different things

A notice that follows a fee demand usually mixes three things. Insurers treat each differently, so separate them before anyone replies.

-   **Your unpaid fees.** PI does not usually pursue money owed to you. A commercial legal expenses policy may, subject to its terms. [Other covers to consider](https://www.hammondpi.com/other-covers.md)
-   **The negligence counterclaim.** Late, uncoordinated or defective design, a budget exceeded, a certificate wrongly issued. This is the core of PI cover, with defence costs where insurers have consented to them.
-   **Fees already paid.** A demand to return or reduce fees, or an allegation of overcharging, is commonly excluded.

The two still need one strategy, because what is said to justify the fees will be read against the defence.

## What architects’ PI wordings ask of you

Wordings differ. These are the points we read first.

-   **Very short notice.** Some wordings cover adjudications only if insurers have written notice within a very short time, sometimes two working days, of the notice arriving or of your first learning that one was intended. A threatening email can start that period before any formal notice exists.
-   **The procedure.** Cover may depend on the adjudicator being independent and the timetable being no harsher than the statutory Scheme. A bespoke clause in a client’s appointment can fail that test.
-   **Consent to costs.** Costs incurred before insurers agree to them are not usually covered. Instructing your own solicitor first can leave you paying for that work.
-   **Finality.** Agreeing that the adjudicator’s decision will be final and binding may need insurers’ consent, because they may want to challenge it later.
-   **Circumstances.** A client that withholds fees after complaining about your work can be a circumstance to notify, whatever your own view of the complaint.

## What to do before you chase the fees

1.  Read the file for complaints. If the client has criticised the design, the programme or the cost, tell us before the final demand goes out.
2.  Let us notify the complaint to insurers as a circumstance first. A counterclaim that arrives later then has a policy to attach to.
3.  Check the adjudication clause in the appointment: who nominates the adjudicator, what timetable applies and whether the client amended it.
4.  Put the record in order: the appointment, the drawing issue register, the brief and budget, each change the client asked for, and the fee account.
5.  If a notice arrives, send it to us the same day with the earlier correspondence, and note when you first knew adjudication was intended.
6.  Do not reply, admit anything or agree procedure until insurers have appointed solicitors.

## After the decision

An adjudicator’s decision is not the end. Under the Scheme the parties must comply with it until the dispute is finally resolved, and either side can still take the dispute to court or arbitration. Findings about your design made in a fast fee adjudication can shape what follows, which is why insurers want to be involved from the first notice and not from the result.

Where a fee dispute turns into a claim, we would put the matter to insurers, press for solicitors to be appointed inside the timetable and stay involved until it is resolved. [Claims support](https://www.hammondpi.com/claims-support.md)

## About to chase an unhappy client?

Call us before the final demand goes out, so any counterclaim is notified in time and defended properly.