Insights for quantity surveyors

# The adjudication clause in a quantity surveyor’s PI policy, taken apart

Adjudication is fast by design, and surveyors’ PI wordings answer that speed with strict conditions. For a quantity surveyor the clause matters twice: in the employer’s disputes you administer, and in disputes under your own appointment.

Why it mattersThe clauseTwo working daysYour appointmentStarting oneThe first day

Guidance only. Cover depends on your own policy wording; speak to us about your position.

## Why adjudication reaches a quantity surveyor twice

First, you work inside other people’s adjudications. As contract administrator or employer’s agent you issue the valuations, payment notices and pay less notices that contractors adjudicate over. If the employer loses because a notice was late, it may look to you.

Second, your own appointment is a construction contract. The Construction Act treats an agreement to do surveying work in relation to construction operations as one ([section 104](https://www.legislation.gov.uk/ukpga/1996/53/section/104)), so your client can refer a dispute about your advice to adjudication at any time.

The timetable is short. The dispute is to be referred within seven days of the notice. The adjudicator must decide within 28 days of referral, which can be extended by up to 14 days with the referring party’s consent, or for longer if both parties agree. The decision binds until the dispute is finally determined ([section 108](https://www.legislation.gov.uk/ukpga/1996/53/section/108) and [Scheme for Construction Contracts, Part I](https://www.legislation.gov.uk/uksi/1998/649/schedule/part/I)). A negligence claim against your practice can therefore be decided, and payable, within weeks of the first notice.

## The clause, part by part

Wordings differ, but the RICS minimum policy wording shows the usual shape ([RICS minimum policy wording](https://www.rics.org/regulation/regulatory-compliance/professional-indemnity/pii-in-the-uk)). Read your own wording for each of these parts.

The parts of an adjudication clause in a surveyor’s PI wording

Part

What it usually says

What it means for a QS

Cover for the decision

The policy covers liability arising from an adjudicator’s decision, provided the conditions below are met.

Insurers accept a result reached at speed. The conditions are what they ask in return.

Two working days

It is a condition of cover that you tell insurers within two working days of receiving a notice of adjudication.

The period runs from receipt by the practice, which may be days before a director reads it.

Consent to start

You must not start an adjudication yourself without insurers’ consent where it could lead to a claim.

An adjudication for unpaid fees often draws the answer that your advice was negligent.

Timetable

Adjudications run to a timetable more onerous than the statutory Scheme are excluded.

A bespoke appointment with a shorter decision period can take the whole adjudication outside cover.

The adjudicator

Many wordings expect the adjudicator to be independent.

An appointment that names the client’s own adviser as adjudicator needs checking before you sign.

## Two working days in practice

Two working days is shorter than most firms’ post routine. A notice may be emailed to the project surveyor on a Friday afternoon, sent to a registered office you rarely visit, or addressed to someone on leave. By the time a director sees it the period may have gone.

What late notice does depends on the wording. Where the notice period is a condition precedent, insurers may be entitled to refuse the claim however strong your defence.

-   Tell every member of staff that a notice of adjudication goes to a named director on the day it arrives.
-   Check who watches the registered office address and shared mailboxes during holidays.
-   Keep our contact details with the policy schedule, and send us the notice itself, not a summary.

An adjudication between employer and contractor is different. You are not a party, so it is not a notice against you. But if the dispute is about your valuation or your notice, it is likely to be a circumstance and should be reported as one.

## The adjudication clause in the appointment you sign

The policy clause is tested against the appointment. Before you sign, check four things.

-   **The timetable.** Compare each period with the statutory Scheme: seven days to refer and 28 days to decide. Anything shorter may engage the exclusion.
-   **The adjudicator.** Look for a named individual or nominating body, and ask whether either is independent of your client.
-   **Clauses that bind you to someone else’s decision.** Some appointments say you will be bound by an adjudicator’s decision between employer and contractor, in a dispute you took no part in. A promise of that kind may go beyond your ordinary liability and can fall within the contractual liability exclusion.
-   **Silence.** If the appointment has no compliant adjudication terms, the statutory Scheme applies. That is the timetable the exclusion is measured against.

We read these clauses against your wording as part of a [contract review](https://www.hammondpi.com/contract-reviews.md).

## Before you adjudicate for fees, or help the employer adjudicate

Recovering fees is not what PI is for, and many wordings exclude claims for the return or reduction of fees. But a client pursued for fees often replies that your cost advice was negligent. That allegation is a PI matter, which is why insurers want to agree before you start.

The same thinking applies when a payment notice has been missed. In _S&T v Grove_ the Court of Appeal confirmed that an employer without a valid notice must pay the notified sum, and can adjudicate the true value afterwards ([\[2018\] EWCA Civ 2448](https://caselaw.nationalarchives.gov.uk/ewca/civ/2018/2448)). If that second adjudication recovers the overpayment, any claim against you is smaller. Our approach would be to ask insurers to agree, where the wording allows, that supporting it is mitigation, and to check the contractor’s solvency at once.

## What to do the day a notice arrives

1.  Record the date and time the notice was received, and by whom.
2.  Send us the notice, your appointment and the policy schedule the same day, so that insurers are told within the two working days.
3.  Make no admission and no offer, including on fees, until insurers have agreed the response.
4.  Do not agree an adjudicator, a change of timetable or an extension without insurers’ agreement.
5.  Gather the file: the appointment, valuations, every notice issued with its date, and the correspondence.
6.  Diarise the referral and decision dates, and decide who covers if the lead surveyor is away.

We stay involved until the decision. See [claims support](https://www.hammondpi.com/claims-support.md).

## Received a notice of adjudication?

Send it to us today, with your appointment, so insurers hear within the two working days your policy may allow.