“Ensure compliance”: the appointment wording that can outrun a Principal Designer’s PI
The Building Regulations ask a Principal Designer to take all reasonable steps. Many appointments ask you to ensure, procure or warrant that the design complies. The difference is a few words, and it can be the uninsured part of a claim.
Guidance only. Cover depends on your own policy wording; speak to us about your position.
What the regulations actually ask
Regulation 11M sets the Building Regulations Principal Designer’s duties. You must plan, manage and monitor the design work. You must coordinate it “so that all reasonable steps are taken” for the design to comply if built. And you “must take all reasonable steps to ensure” that designers cooperate, that their work is coordinated and that they comply with their own duties (Building Regulations 2010, regulation 11M).
The word “ensure” is there, but it is governed by “all reasonable steps”. The duty is about your conduct, not the result. The designers’ own duty to design for compliance is framed the same way (regulation 11K).
The CDM role’s main duty is also qualified. The Principal Designer must plan, manage and monitor the pre-construction phase so that, so far as is reasonably practicable, the project is carried out without risks to health or safety. Two CDM duties are worded more firmly: to ensure that designers comply with their own duties, and that everyone working in the pre-construction phase cooperates (CDM 2015, regulation 11).
What appointments ask for instead
Client drafted appointments often drop the qualification. Typical wording says the Principal Designer shall ensure that the design complies with the Building Regulations, shall procure that all designers comply, or warrants that the completed works will comply.
A RIBA professional feature, published on 26 February 2026, reports that clients are often rejecting RIBA’s Principal Designer contract in favour of bespoke terms, for example making the Principal Designer liable for meeting the Employer’s Requirements. It says this extends the role beyond its statutory scope (RIBA, separate appointments).
The courts can enforce a promise of a result where nobody was negligent. In MT Højgaard v E.ON, decided by the Supreme Court on 3 August 2017, a contractor designed offshore wind turbine foundations to a published industry standard that contained an error. The trial judge rejected the allegation that the contractor was negligent. It was still liable, because a paragraph in the technical requirements called for a lifetime of 20 years ([2017] UKSC 59). A result promised in a schedule can sit beside a duty of reasonable skill and care in the same contract, and prevail.
How PI wordings treat the gap
PI is built around negligence. Wordings for designers typically cover civil liability, then take back liability for breach of contract so far as the duty claimed is more onerous than common law or statute would imply. Liability assumed under an express warranty or guarantee is commonly excluded unless you would have been liable anyway, and guarantees of fitness for purpose usually stay excluded.
Put the appointment and the policy together. If the design does not comply and you were negligent, the policy is engaged. If the design does not comply although you took all reasonable steps, you may still be in breach of an “ensure” clause, and that liability may sit outside the policy. The answer always depends on the wording, which is why we read both documents. The clause guide
The words to look for
Search the appointment, its schedules and any collateral warranty for these.
| Wording | What it promises | The PI point |
|---|---|---|
| “Take all reasonable steps to ensure the design complies” | Conduct. This is the regulation’s own standard | Matches the duty the law imposes |
| “Ensure the design complies” | A result, whatever care you took | May be more onerous than the law would imply |
| “Procure that the designers comply” | A result that depends on other firms | The same point, and you may answer for firms you did not appoint |
| “Warrant that the completed works comply” | A guarantee of the building, including work done after your role ended | May fall within a warranty or guarantee exclusion |
| “Comply with the Employer’s Requirements” | Whatever those documents contain, including performance criteria | Any fitness for purpose requirement inside them is usually excluded |
| “Indemnify the client against any breach” | Payment of the client’s loss whether or not you were negligent | An indemnity can reach further than damages for negligence, and fines and penalties are excluded |
Amendments worth asking for
- Mirror the regulation. Replace “ensure” with “take all reasonable steps to ensure”, in the words of regulation 11M.
- Add an overriding clause: nothing in the appointment imposes a duty higher than reasonable skill and care. Make sure it expressly reaches the schedules.
- Tie every duty to your period of appointment. You cannot coordinate design changes made after you left.
- Limit any indemnity to loss caused by your negligence, or delete it.
- Keep a liability cap and a net contribution clause, and repeat both in any collateral warranty.
- On housing, remember that a term excluding or restricting Defective Premises Act liability is void (Defective Premises Act 1972, section 6).
Clients often say the wording is standard and that nobody else objects. The plain answer is that a promise your PI does not back is only as good as your firm’s own funds, which helps neither side.
If you have already signed
Many firms find an “ensure” clause after the project has started. Send us the appointment. We would compare it with your wording, tell you which promises may fall outside it and, where it matters, ask insurers for their view in writing.
Tell us about onerous terms at renewal too. Insurers ask what share of your work is on bespoke terms, and an accurate answer is part of a fair presentation. Fair presentation explained
At completion the same issue returns in another form, when a client’s form asks you to declare that the building complies. The statement the regulations require is narrower: that you fulfilled your duties while appointed (regulation 16). Our earlier insight covers when to sign and when not to. When to say yes, and when not to sign
Asked to “ensure” compliance?
Send us the appointment before you sign it, and we will mark the promises your PI may not follow.