Insights for project managers
Gateway 2: when the approval period in your programme becomes the claim
The law gives the Building Safety Regulator 12 weeks to decide a valid application for a new higher-risk building. Its own figures to August 2026 show a median of 22 weeks. That gap sits in your programme, and the client relied on it.
Guidance only. Cover depends on your own policy wording; speak to us about your position.
What the regulations say
A higher-risk building has at least seven storeys or is at least 18 metres high, with at least two residential units or use as a hospital or care home (GOV.UK, building control approval for higher-risk buildings). Work cannot start until the regulator has granted building control approval (Higher-Risk Buildings Procedures Regulations 2023, regulation 3). The industry calls this Gateway 2.
The regulator must decide a valid application within 12 weeks of receiving it, or within a longer period agreed in writing with the applicant (regulation 5). An application is valid only if it contains everything regulation 4 requires. For work to an existing higher-risk building, GOV.UK gives a period of up to 8 weeks. It adds that the time taken depends on the quality of the application and the complexity of the work.
What the regulator’s own figures show
The regulator publishes its decision times. These figures cover the 12 weeks to the end of August 2026 (GOV.UK, Building Safety Regulator application data, June to August 2026).
| Type of application | Decisions | Approved | Median time to approval | Still in progress |
|---|---|---|---|---|
| New higher-risk buildings | 50 | 92% | 22 weeks | 147 |
| External remediation | 118 | 89% | 33 weeks | 327 |
| Internal works to existing buildings | 143 | 78% | 32 weeks | 1,082 |
For complex new build cases the median was 33 weeks. The same data shows 141 invalid or withdrawn applications for internal works. The regulator says its medians remain high partly because older applications are still being cleared. Even so, none of these medians is close to the statutory period. A programme that shows 12 weeks as a fixed duration is not supported by the published evidence.
What changed in 2025 and 2026
- Reform of the regulator. In June 2025 the government announced a fast track process, more than 100 new staff and a new body to take over the regulator’s functions, in response to delays (GOV.UK, 30 June 2025).
- The building safety levy. From 1 October 2026 an application must include levy information where the levy applies (regulation 4). GOV.UK says the regulator cannot issue a completion certificate until the levy is paid or a notice of no charge has been issued. That is a new item on the critical path at the end of the project.
- No decision in time. An applicant can ask the Secretary of State to decide an application the regulator has not determined in time (Building Act 1984, section 30A). If it does not, the application can be treated as rejected (regulation 55). In practice an extension may be agreed instead, and each one belongs in your reports.
Where the project manager is exposed
The client applies, and stays legally responsible even when it nominates someone else to submit. Where someone applies for the client, the client must sign a statement confirming the information is correct. In practice the project manager often assembles the pack: plans, a competence declaration, a construction control plan, a change control plan, a mandatory occurrence reporting plan, a Building Regulations compliance statement and a fire and emergency file (regulation 4).
- The programme. You showed the statutory period as the duration and attached no risk to it.
- The application. You co-ordinated it, a document was missing or thin, and it was found invalid or rejected. The regulator can reject an application that lacks the detail to show compliance (regulation 7).
- Approval with requirements. Work on the affected part cannot start until the requirement is met, and nobody was tracking it.
- Change control. A major change stops work on that part until it is approved. A late design change you managed becomes a stoppage.
- Completion. The regulator has 8 weeks to decide a valid completion certificate application (regulation 41). Handover dates promised to purchasers and funders depend on it.
How a PI wording may treat a gateway claim
Programme advice is a professional service, and a claim that it was negligent is the kind of claim PI exists for. Three clauses decide how well the policy responds.
- Fire safety. Some wordings exclude or limit claims in any way related to the fire safety of a building. A dispute about a delayed approval may be drawn into that definition, with an aggregate limit and defence costs inside it. Fire safety exclusions explained
- Contractual liability. An appointment that promises an approval date, or a start on site by a date, goes beyond reasonable skill and care. That extra may not be insured.
- Professional business. If you assemble applications or sign statements as a dutyholder, insurers need to have been told. Principal designer: when to sign
A rejected application on a project with a fixed funding date can be a circumstance. Tell us when it happens, not when the letter arrives.
Six things to put in writing now
- Show approval as a range on every programme, and state the assumption behind the earliest date.
- Give the client the regulator’s published medians, with their date, when you advise on the range.
- Record who assembles each part of the application and who checks it for completeness before it goes.
- Log every extension agreed with the regulator and every requirement attached to an approval.
- Put the levy and the completion certificate on the programme as separate items.
- Check your appointment for any promise of dates, and send it to us if you find one. Contract reviews
Managing a higher-risk building?
Tell us your role and what your appointment says about approvals, and we will check how your policy would treat a delay.