Safety occurrence reports on higher-risk buildings: the regulator, your insurers and the clock
On a higher-risk building the Principal Designer must look for safety occurrences in the design and report them to the Building Safety Regulator, in writing within 10 days. The report is a legal duty. It is also something your PI insurers need to hear about.
Guidance only. Cover depends on your own policy wording; speak to us about your position.
A reporting duty that sits on you
Since 1 October 2023, work on a higher-risk building in England has carried a duty that ordinary projects do not: mandatory occurrence reporting. For design and construction, a higher-risk building is one of at least 18 metres or seven storeys that has two or more residential units, or is a hospital or care home (GOV.UK, submitting mandatory occurrence notices and reports).
The duty falls on two “principal dutyholders”: the principal contractor and the Principal Designer (Higher-Risk Buildings Procedures Regulations 2023, regulation 35). Before construction begins they must set up a system for the prompt reporting of safety occurrences, and keep it running. Designers and contractors must be told how it works before they start. And the Principal Designer must inspect the design work for safety occurrences at an appropriate frequency throughout the construction phase (regulation 32).
So the role does not end when the drawings are issued.
What counts as a safety occurrence
For a design, a safety occurrence is an aspect of the design relating to the structural integrity or fire safety of the building which, if built, would meet the “risk condition”. That condition is met where use of the building, without the matter being remedied, would be likely to present a risk of a significant number of deaths, or of serious injury to a significant number of people (regulation 35).
The regulator’s guidance gives examples, including structural defects that are discovered, fire safety products that are non-compliant, incompatible or incorrectly installed, and faults in design plans caused by software or human error. It says a report is generally still required where the problem is put right at once (GOV.UK).
The test does not ask whose design it was, or whether anyone was negligent. A Principal Designer who designs nothing may still be the person who has to report a fault in the structural engineer’s detail.
What to send, and when
The duty to report applies when a safety occurrence happens during the construction phase, and starts when you become aware of it.
| Step | When | What it contains |
|---|---|---|
| Notice to the regulator | As quickly as practicable and without undue delay | The regulator’s guidance asks for contact details, the building’s address, the date identified, a brief description and any immediate safety action |
| Written report | Within 10 days of becoming aware | Date and time of the occurrence, site address, your contact details, the type and details of the occurrence including the nature of the risk, and any remedial or mitigating measures |
| After the report | When the regulator has reviewed it | It may ask for more information, decide that no report was needed, or start an investigation. Investigations carry cost recovery charges |
Sources: regulation 33; GOV.UK, submitting notices and reports. If a report has already been submitted for the same occurrence, the guidance says a further one is not needed, and that you should obtain a copy of the existing report.
What the report can be used for
Failing to follow the reporting procedure is a criminal offence under the Building Act 1984 (section 35). The regulations give one specific defence: that you reasonably believed the other principal dutyholder had already notified the regulator and sent the written report (regulation 34).
Information given under the procedure generally cannot be used against the person who gave it in criminal proceedings. There are exceptions, including proceedings for failing to report and for giving false or misleading information (regulation 33). The regulation says nothing about civil proceedings. A report is a dated, written statement by the Principal Designer that an aspect of the design was unsafe. A later claimant’s advisers will want to see it.
That is no reason to delay or dilute a report. It is a reason to keep it to the facts the regulations ask for, and to leave out opinions about who was at fault.
Why insurers need to hear the same day
PI wordings require you to notify claims and circumstances as soon as reasonably possible. A circumstance usually includes becoming aware of a shortcoming in your work, or of something likely to lead to a claim. A safety occurrence in a design you coordinated is hard to describe as anything else, even where another firm produced the detail.
Four points in the wording matter:
- Late notice. If the regulator hears now and insurers hear only when a claim arrives years later, they will ask why.
- Admissions. Wordings commonly bar admissions of liability without insurers’ consent. A factual statutory report is a different thing, but insurers should see it. Send it to us in draft if time allows, and never let that hold up the report.
- Fire safety terms. A safety occurrence concerns structure or fire safety by definition. If it concerns fire, a fire safety endorsement may restrict the cover. Fire safety exclusions explained
- Investigation costs. Fines and penalties are excluded. Whether the wording helps with the cost of responding to an investigation depends on its inquiry and criminal defence clauses, which usually need insurers’ prior written consent.
What we would do with you
- Call us the day you form the view that the test may be met. We would notify insurers of a circumstance at once.
- Give the regulator notice without waiting for the insurance discussion. The statutory clock does not stop for it.
- Draft the written report from the list in regulation 33: facts, dates, the nature of the risk and the remedial measures.
- Record how your inspections found the problem. Finding it is evidence that you were doing the job.
- Tell the client and the principal contractor through the agreed reporting system.
- Leave questions of responsibility between the designers to insurers’ solicitors.
Before your first higher-risk appointment, tell us how your reporting system works and who runs it. How we support a claim
Found something you may have to report?
Call us the same day, so the report to the regulator and the notification to insurers go together.